The Naglee Avenue project is officially under construction. The following dates are a high-level overview of the project schedule
Total Construction Period: 2/8/2021 to 3/11/2021
Pavement “Prep” Work: 2/8/2021 to 2/17/2021
Repaving Work: 2/17/2021 to 2/24/2021
Temporary Striping: 2/24/2021 to 3/6/2021
Final Striping: 3/8/2021 to 3/11/2021
Thank you for your interest in the Naglee Avenue Project. We will continue to provide updates as the project progresses.